Electrical panel upgrade in a Burnaby home — from 100A to 200A to support a new heat pump system
100A → 200A
Panel Upgrade
~4 Hours
Power Outage Time
1 Day
Project Duration
40 Circuits
Future-Ready Spaces
3 project photos
Photos documented for this case study
5 scope items
Equipment and work documented below
Burnaby, BC
Completed Summer 2024
The project
Before Grove Mechanical could install a new Mitsubishi heat pump in this Burnaby home, the electrical panel needed to be upgraded. The existing 100A service — standard for homes built in the 1960s and 70s — was insufficient to handle the heat pump's startup load alongside the home's existing appliances. Grove Electric performed a full 200A service upgrade: new meter base, new main panel, updated breakers, and BC Hydro coordination. The upgrade was completed in one day, and the heat pump was installed the following day.
A 200A service upgrade requires a permit from the local authority and coordination with BC Hydro for the meter pull. Grove Electric managed all permit applications and BC Hydro scheduling to ensure the upgrade was completed in a single day with minimal power outage time for the homeowner.
During the panel upgrade, Grove Electric discovered original knob-and-tube wiring in the attic — a common finding in homes of this era. The homeowner was advised, and the affected circuits were replaced before the new panel was energized, ensuring code compliance.
The homeowner had scheduled the heat pump installation for the following day. Grove Electric coordinated closely with the HVAC team to ensure the dedicated circuit was ready and the panel was fully commissioned before the HVAC crew arrived.
The 200A upgrade was completed in one day with a 4-hour power outage. The heat pump was installed the following day and commissioned without any electrical issues. The homeowner now has a modern, code-compliant electrical system with room to add an EV charger, hot tub, or additional circuits in the future — and a heat pump that qualifies for the full CleanBC rebate.
Most modern heat pumps require a dedicated 240V circuit with 30–50A capacity. If your home has a 100A panel with most circuits already in use, you may not have capacity for the additional load. Grove Mechanical always performs an electrical assessment before quoting a heat pump installation — if an upgrade is needed, Grove Electric can complete it as part of the same project.
A typical 200A service upgrade takes one full day. The power is off for approximately 3–5 hours while the panel and meter base are replaced. BC Hydro must pull the meter before work begins and reconnect it after — Grove Electric coordinates this scheduling as part of the project.
A 200A service upgrade in the Lower Mainland typically costs between $2,500 and $4,500 depending on the complexity of the existing service entrance, the panel location, and any additional wiring work required. Grove Electric provides a fixed-price quote before any work begins.
200A Main Panel
Square DQO Load Centre
200A, 40-space, surge protection, Arc Fault breakers throughout
200A Meter Base
MilbankReplaced original meter base to match new service rating
Service Entrance Cable
Grove ElectricNew 2/0 aluminum service entrance cable from meter to panel
BC Hydro Coordination
Grove ElectricPermit pulled, BC Hydro notified, meter pull and reconnect arranged
Dedicated Heat Pump Circuit
Grove Electric40A/240V dedicated circuit for Mitsubishi heat pump outdoor unit
3 project photos from this documented installation
5 installed equipment and scope details
3 on-site challenges explained
Completed in Burnaby, BC